Description
• Design and installation of a new 5.5 million BTU gas heater
• Refurbishing of two large gas heaters with Honeywell 7800 controllers
• LNG analyzer design and installation
• Under-tank heater design and installation
• Several piping design and upgrade projects

Scope of Work
• Complete engineering design and bid documents
• Project schedules, cost estimates, process hazard reviews
• Construction support
Challenges
• Existing aging facilities
• Small window for shutdowns
Keys to Success
• Integrated project team
• Value engineering